Curillinque Hydropower Station

Curillinque hydropower station in Chile is owned by Enel. The station was commissioned in 1993 and was equipped with one Francis turbine of 89 MW at a net head of 114 meters. 

In 2021, Aker Solutions carried out model testing and upgrading of the unit to improve operational stability over a larger power range. The station had previously been experiencing severe vibrations at higher outputs.

After testing and replacement of most non-embedded parts, the unit was recommissioned in 2023. The upgrade significantly increased the area and range of operate, removing the vibrations, and enabling improved operational flexibility.